Start-up for Iggesund’s recovery boiler

At eight a.m. on Tuesday 12 June Iggesund Paperboard’s new recovery boiler and turbine came on line at Iggesund Mill. At almost 240 million Euro, this is the mill’s largest investment ever. The start-up also meant that the project team, including almost a thousand contractors, reached the finish line exactly on schedule.

 

“It feels terrific that the project has come to a successful conclusion, and that we’ve done so both within the projected time frame and without any significant mishaps or accidents,” comments Lennart Wanberg, Iggesund’s manager of the project. “We’ve focused very strongly on safety, not least because people have been working up to sixty metres above the ground.”

 

The recovery boiler is the “heart” of a sulphate pulp mill and serves this function at Iggesund Mill, which produces the world’s leading quality paperboard, Invercote. Despite the boiler’s key role, Iggesund managed the instantaneous switchover from the two old recovery boilers to the new one without any interruption in the production process. The boiler is also built to withstand higher pressure than any other recovery boiler in Europe, and will work with a steam pressure of 110 bar. 

 

This increased pressure makes it possible to generate more electricity. The new turbine should be able to supply 520 GWh/year and in the longer term also make Iggesund Mill completely self-sufficient in electricity. When exactly the latter will occur depends very much on how the pulp production develops. Currently the mill has a permit to produce 355,000 tonnes of pulp annually, but has applied for permission to increase yearly production to 420,000 tonnes. 

We use cookies on the website. Read about it

I accept cookies
Holmen.com Print Cookies   |   MyPages